Many persons may hear about the drilling mud solids control. But conerning how to purify the drlling mud, not so many people know well about it. Here we would like to talking about the drilling mud 4 stages solids control and 5 stages purification.
First stage for solids control & purification
Shale shaker is widely known as a solids control equipments used in drilling projects. It is a very basic equipment that could separate the drilling cutting more than 250 microns by fine mesh screens. During this stage, actually, the solids control and purificaion happens at the same time. Just as its name implies, solids control is separate the solids from the fluids, while the drilling cutting and other large size impurities being separated, the drilling mud is purified.
 shale shaker
written by GN Desander Desilter
\\ tags: drilling mud cleaning equipment, mud purification, mud system, solids control stages
Centrifuge is a widely used device in oil & gas drilling mud system. It always adopts decanter principle to separate suspension liquid. In the tank system, centrifuge is located as the fourth stage handling equipments to treat the drilling mud out from the mud cleaner.
MI-Swaco is really a world famous solids control specialist either in products quality or in service. Known to all the persons in solids control field, MI-Swaco’s equipments also have a higher price. Many customers inquiried us for the equivalent equipments of MI-Swaco, Derrick and some other famous brand.
 Well drilling centrifuge
Continue reading »
written by GN Desander Desilter
\\ tags: decanter centrifuge, mud recycling system, solids control equipments
GN brand decanter centrifuge is a separation equipments used in the drilling mud recycling system. In this period of time, we have sent many sets of this type centrifuge to USA, Latin America and other area of the wrold.
Decanter centrifuge always used in the large system like the mud recycling system matching the drilling rig for oil & gas, geothermal etc. It is used as the 4th stage equipment to treat the drilling mud feeded by a submersible pump from the desilter tank compartment. Under normal condition, the centrifuge could separate the solids particals with the size of 7 microns. If a high speed variable frequency centrifuge is taken into application, even partical with size 2 microns could be removed out.
 drilling mud decanter centrifuge
Here the problem come out. In the complete 4 stage treatment process, from shale shaker to mud cleaner (a combination of desander and desilter), then to decanter centrifuge, the solid particals separated from the mud is more and more smaller. So, customer often learn our centrifuge according to the partical size. It is a fact that the decanter centrifuge have a good performance in separating the tiny particals, but when it is working, the most important factor is the density of the particals and medium, rather than the partical size. And the density difference should be relative bigger. Once a customer who want to use this type centrifuge to separate microbes with size from 2 microns to 20 microns cultivated in water. As we can not confirm the density difference, we haven’t proposed our centrifuge at last. Continue reading »
written by GN Desander Desilter
\\ tags: decanter centrifuge, solids control equipments, solids control system
In order to learn well about Trenchless Drilling Mud System, we have to know what is trenchless drilling technology. Trenchless technology is a type of subsurface construction work that requires few trenches or no continuous trenches. Because of the minimal disruption to surface traffic, business, and other activities, trenchless drilling technology is widely used in installation of new or replacement or rehabilitation of existing underground infrastructure.
 trenchless drilling mud system
Why Need A Mud System in Trenchless Drilling
HDD is a well known type of trenchless drilling, in the drilling project, we will need the horizontal directional drilling rig. In order to protect the rig bit and make it easy for drilling, a good number of drilling mud will be used. Therefore, the need for mud system is emerged. During a large treating capacity trenchless drilling project, mud system is only partial unit of it. We can also find drill rig, mud pump and other equipments. Continue reading »
written by GN Desander Desilter
\\ tags: HDD, HDD mud system, mud recycling system, solids control equipments
Shortly before, a client from Indonesia told us they plan to implement a pitless drilling system in their project for disposal the unused drilling mud.
What is Pit Less Drilling System
 500GPM Hydraulic Jack up solids control system
Pit less drilling system is also call closed-loop drilling system. It employ a suite of solids control equipment to minimize drilling fluid dilution and provide the economic handling of the drilling wastes.
In the pit less drilling system where a reserve pit is not required, used drilling mud are recycled, and solid wastes can be landfarmed, hauled off or injected downhole.
Typcical Pitless Drilling System include:
1. Series of Linear motion shale shaker
2. Mud cleaner
3. Centrifuges followed with dewatering system: in the dewatering system, the High speed dencanter centrifuge and cutting drier are included.
written by GN Desander Desilter
\\ tags: pitless drilling system
System general information
This solids control system including one tank mounted with 1) Shale shaker, 2) Mud cleaner, 3) Mud agitator, 4) Centrifugal pump, 5) Mud mixing pumpetc. Combined drilling mud recycling, mixing and storage as complete solids control system for small well drilling rig
GN500GPM Mud sytem detailed information
1)Handing Capacity: Up to 550 Usgpm (2080 litres/min) for total system
2)3 Phase Cleaning: With 2.6㎡ first phase shaker, and 2×8″ Desander cone, 8x4inch Desilter cone. With 2.6㎡ drying screen for mud cleaner. Specifically for high solids content and fine solids.
3)Cut Point: Designed to achieve a cut point of 16 microns
4)Transport Dimensions: Mud Tank With Attachment: 9000L x 2400W x 4300H (Tank folded for transport,walks ,hand rail holded on tank) Shaker dimention: 2.45m X 2m X 1.7m Mud Cleaner Dimention: 2.45m X 2m X 2.5m This design and dimension provide more convenience for transportation and handling
5)Capacity: Total storage capacity 4500Gallons,Dirty mud:1700Gallons,Clean mud:2800Gallons.
6)Power: Explosion proof for all the motors and control panel.Integral control panel for all electrical functions. Total power for all equipments:188kva,genertor Recommended:≥210kva
7)Sea Transport: Two 40feet Container for all items and remaining space for spare parts.
8)Mixing Function: High speed continuous mixing facility incorporated.
9)Integral charge pump to supply clean mud back to the drilling rig.
10)Mud mixing in cleaning mud compartment(Mixing Compartment) with 7.5kw mud agitator.
 GN500GPM rig solids control system for sale
GN500 GPM mud system sales point
Cleaning Tank is divided into 3 compartment,1# Shaker compartment,2# De-sander compartment,3# Mixing compartment.
1)Continues feeding of dirty slurry from mud pit to Shale Shaker. The 100YZ100-30 Submersible slurry pump feed slurry from mud pit to GNZS70-3 Shale Shaker at capacity of 615 GPM .Slurry pump is made from Cr26 Abrasion resistant
Alloy which allow users to pump high solids content fluids.
2)Pre-screening of the returned mud using GNZS70-3 Shale Shaker.This shaker can handle a throughput of more then 615 USgpm and is designed to remove particles down to 250 microns(60mesh), 7G force linear motion GNZS70-3 Shale Shaker with big screen area(2.6㎡) especially using frame pyramid screen treating capacity increased which allows user to use big mesh size for fine solids, and decrease the solids content and reduce solids load for Mud cleaner.
3)Secondary and third cleaning of the returned mud using a GNZJ70-3 (8″x2 + 4″ x8) Mud Cleaner.1# SB5×4-14 Centrifugal pump feed mud from 1# Shaker compartment to feed 8″x2 de-sander cones, where the particles larger than 50 microns are separated out by centrifugal force from desander cone nipple, and get down to GNZJ70-3 mud cleaner bottom shaker with a finer screen(150/200mesh) which again produces a virtually dry product. Major fluids with particle size less than 50microns goes to 2# De-sander compartment. This is the 2nd phase solids control.
2# SB5x4-14 Centrifugal pump suck mud from 2# desander compartment and feed to 4″x8 desilter cones. where the particles larger then 16 microns are separated out by centrifugal force from desilter cone nipple,and get down to GNZJ70-3 mud cleaner bottom shaker with a finer screen, which again produces a virtually dry product. Major fluids with particle size less then 16 microns goes to
3# Mixing compartment. This is the 3rd phase solids control.
Continue reading »
written by desander desilter
\\ tags: 500GPM mud system, china manufacturer, desander, desilter price, drilling rig system, fluids solids control for sale, mud cleaner, oil well drilling solids control
Workover rig application
Workover rig is one kind of drilling rig also. It is widely used in oil and gas well drilling. Workover is used to refer to any kind of o & g well intervention involving invasive techniques, such as wireline, coiled tubing or snubbing. More specifically though, it will refer to the expensive process of pulling and replacing a completion
The workover begins by removing the wellhead and possibly the flow line then lifting the tubing hanger from the casing head and thus beginning to pull the completion out of the well.
 200HP Workover rig
If the packer is retrievable it can be released easily enough and pulled out with the completion string. The string will almost always be fixed in place by at least one production packer.
Workover rig mainly including 200HP, 350HP, 450HP, 55oHP,650HP, 750HP.
200HP work over rig
Actually, 200HP work over rig is similar with 350HP work over rig. For 200HP work over rig we also need to treat it as common drilling rig. Their basic principle is almost same
To give 200HP workover rig better performance we also need drilling mud system to realise solids control or drilliing fluid reuse. We just got one inquiry from clients. They are doing oilfield service.
 Workover mud system
They inquire us 200HP workover rig mud system price. Please find following information on this workover rig mud sytem
200HP Workover rig mud system for sale
This system including complete set equipments:
1. GNPS703 BEM Shale shaker one set
2. GNPJ703 BEM Mud cleaner one set
3. SB6X5-12 Centrifugal pump two sets. As feeding pump for desander and desilter separator
4. JBQ7.5 Mud agitator three sets, as well as NJQ80-3 Mud gun three sets
Continue reading »
written by GN Desander Desilter
\\ tags: 200HP workover rig, workover mud equipments, workover rig for sale, workover rig manufacturer, workover rig mud system, workover rig sytem price
Movable drilling fluid system is a drilling rig mud system designed to be monuted on a trailer or a truck. This kind of system is popular for its convenience and easy handling on transportation
Movable drilling fluid system can be used in widely industry similar as other solids control system. Such as oil and gas drilling fluid process, HDD mud recovery system, work over rig solids control unit, etc. Please find following information on the movable system for sale
Design on movable fluid system
The movable drilling fluid process system is same as common systems. Usually it including 4-phase process. Shale shaker both linear motion or BEM shaker, then come to desander, desilter, decanting centrifuge. Also maybe including jet mixing unit.
 Movable drilling fluid system
Considering treating capacity as well as transportation we design mud tank and system more compact. On system tank, we configure GNZS or GNPS shale shaker, GNZJ or GNPJ Mud cleaner, LW series centrifuge, mud mixing hopper, centrifugal feeding pump, complete explosion proof control panel, all necessary accessories on one oil skid mounted tank
Equipments information on system for sale
It is same as the system on our CIPPE drilling show. The detail on equipments are as following:
- Mud tank, L 14 x W 2.8 x H 1.8m
- Shale shaker, two GNPS703
- Mud conditioner, GNZJ703
- Decanting centrifuge, LWF450x1000N
- SLH mud hopper mixing pump
- Centrifuge pump for desander and desilter hydrocyclones
Continue reading »
written by GN Desander Desilter
\\ tags: Drilling fluid rycycling unit for sale, fluid process plant for sale, Mobile system, Movable drilling fluid system, Movable mdu tanks system, solids control system price
This trailer mounted mud system is for oil well drilling. The rig can drill 3-4km. One of our client requests us to configure following trailer mounted mud system for 750HP rig. As we know, the drilling rig can be manufactured as trailer mounted also. Regarding to industry terms, 750HP rig can be said 175T drilling rig also.
I. Mud system configuration
This trailer mounted mud system requires about 600GPM capacity. Following design is basic information on 750HP rig mud system
1. Shale Shaker Tank in trailer mounted system
+/-300 bbls with following compartments, Trip compartment : +/-50 bbls with readout on drillers console and plumbed for recirculation, Sand Trap : +/-50 bbls, Degasser Tank : with lo-pressure mud gun,+/-100 bbls capacity. Mud cleaner tank : with 10 hp agitator & 10- pressure mud gun, +/-100 bbls capacity
2. Suction Tank
+/-350 bbls with following compartments; Suction compartment: +/-100 bbls with 10 hp agitator & lo-pressure mud gun. Intermediate compartment: +/-100 bbls with 10 hp agitator & lo – pressure mud gun, Mixing compartment: +/-100 bbls with 10 hp agitator & lo-pressure mud gun. Pill Tank : +/-50 bbl with 10HP Agitator & low pressure mud gun, also should includ mixing hopper: with mixing pump & lines to all compartments
 Trailer Mounted Mud System from DMS
3. Reserve Tank
With following compartments; Mud Tank :+/-125 bbls with 10 hp agitator & lo-pressure mud gun. Mud Tank :+/-125 bbls with 10 hp agitator & lo-pressure mud gun. Water Tank : +/-100 bbl. Mud hopper : with mixing pump & lines to all compartments
4. Swab or Test Tank
+/-300 bbls with +/-equal compartments, each plumbed for separate discharge to vacuum truck or water tank. Complete with minimum 32 ” Poor-Boy Degasser with proper vent, fluid leg and inspection hatch.
II. 750HP rig trailer mounted mud equipments detail
1. Shale Shaker in system Tandem shale shaker mounted on shaker tank. The capacity will up to 1056GPM. Shaker screens will be provided together with shakers. The shale shaker can be linear motion or balanced elliptical motion shaker.
 Centrifugal Sand Pump
2. Mud Cleaner: Require two 10” desander cones and ten 4” desilter cones. The total capacity is up to 880GPM. Under set shaker can be linear motion or BEM type
3. Independent centrifugal sand pumps: These centrifugal pumps are used as charge pumps for mud cleaner cones. They are applied to mud transfer and mud mixing. Totally need 4 centrifugal pumps. The power should be 45KW, charging capacity should be 200m3/h.
4. Mud/Gas Separator : Poor-Boy degasser ,vertical mounted with baffles, fluid leg, inspection hatch. Holding 24″ OD x 14′ high with 4″ OD inlet from choke manifold, 8″ OD return line to shale shakers, 8″ OD vent line, 4″OD drain & all necessary piping to connect to choke manifold, shale tank & flare line, etc.
Continue reading »
written by GN Desander Desilter
\\ tags: 175T rig mud system, 750HP rig system, movable system, rig system manfuacturer, trailer mounted mud process unit, trailer mounted rig
 workover rig mud tank system in India
If you do workover drilling service and in need of mud tank system, pls contact GN solids control.
written by GN Desander Desilter
|